A video of Vidrala’s record-breaking glass furnace reconstruction at Crisnova Vidrio plant is now available. The work took place in a record time of 59 days and, thanks to good practices in prevention and safety, resulted in zero accidents.
Spanish group Vidrala has published a video of a record-breaking glass furnace reconstruction.
The reconstruction of a furnace at its Crisnova Vidrio plant in the town of Caudete took place in a record time of 59 days.
Good practices in prevention and safety resulted in zero accidents.
Equipment used included 3600 tons of refractories, 200 tons of iron, 15 kilometres of electrical cable, 700 metres of conveyors and almost 30 trucks to equip the cold end. A total of 35 international suppliers and more than 400 workers were involved.